°ÄÃÅÁùºÏ²Ê¸ßÊÖ

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization publication(s) that you have requested. °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization.

For more information, see our Privacy policy.

News & Media

Latest °ÄÃÅÁùºÏ²Ê¸ßÊÖ Newsline

  • Fusion supply chain | A glimpse into the future for commercial fusion reactors

    Most of the USD 7 billion in investment in private fusion initiatives has gone to companies that are building devices from the ground up. But recently, another [...]

    Read more

  • Outreach | °ÄÃÅÁùºÏ²Ê¸ßÊÖ @ October science festivals

    Every October, before schools pause for two weeks of holiday, towns and cities in France open their municipal spaces to scientific experts of all stripes who ar [...]

    Read more

  • Image of the week | °ÄÃÅÁùºÏ²Ê¸ßÊÖ Director-General visits Russia

    The °ÄÃÅÁùºÏ²Ê¸ßÊÖ Director-General was in Russia last week, meeting with stakeholders and holding technical meetings with colleagues in Moscow and Saint Petersburg. As [...]

    Read more

  • Image of the Week | Sector 5 is on its way

    The first vacuum vessel sector produced in Europe travelled last week between Monfalcone, Italy, and the French port of Fos-sur-Mer. The 440-tonne component had [...]

    Read more

  • Anniversary | °ÄÃÅÁùºÏ²Ê¸ßÊÖ Document Management system turns 20

    Whatever its nature, every large project generates huge numbers of documents. And when project collaborators operate from different countries, as was the case f [...]

    Read more

Of Interest

See archived entries

A five-storey "Diagnostic Hotel"

Each diagnostic system will be assigned a room on one of the three central floors of the Diagnostics Building. Top and bottom floors will house the ventilation systems, cooling units and cable trays. (Click to view larger version...)
Each diagnostic system will be assigned a room on one of the three central floors of the Diagnostics Building. Top and bottom floors will house the ventilation systems, cooling units and cable trays.
Diagnostic instruments will be distributed throughout the °ÄÃÅÁùºÏ²Ê¸ßÊÖ vacuum vessel, as near as possible to the plasma in order to capture information for plasma control, machine protection, and an understanding of plasma physics.

But the back ends—the electronic and information systems that will receive, record and interpret signals from the operational arena—must be situated at a distance, well protected from the nuclear and thermal loads of the Tokamak.

In February work was completed on the concrete basemat for the Diagnostics Building, a 40 x 80 metre, five-storey structure that will house most of the back-end systems for °ÄÃÅÁùºÏ²Ê¸ßÊÖ diagnostics. Situated outside of the bioshield that will surround the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Tokamak, but part of the same suite of buildings to be built on nuclear foundations in the Seismic Pit, the Diagnostics Building will remain accessible to technicians.

"On an average day, no frequent human intervention will be necessary within the Diagnostics Building," explains Victor Udintsev, who leads the Common Port Plug and Engineering Sub-Section. "Data coming from the diagnostics will be monitored from the , where approximately 20 percent of operators will be assigned to diagnostics. But technicians can enter the building and spend time in the event that repairs or testing are necessary."

The concrete basemat for the Diagnostics Building, located to the south of the machine, was completed in February. (Click to view larger version...)
The concrete basemat for the Diagnostics Building, located to the south of the machine, was completed in February.
Walking through the hallways of the Diagnostic Building would feel a little like walking along the corridors of a hotel—flanked on every side by closed doors with room numbers and the names of the systems enclosed within. "One room has typically been reserved for every system," says Victor. "Behind the doors, you'd find the complete back-end systems, including electrical cubicles, electronics, computers and control units."

And, despite its name, in addition to back-end diagnostics the Diagnostics Building will also house CODAC and other systems.

Diagnostic signals will be transported out of the Tokamak an average of 25 metres, and in some cases as much as 40 metres, along waveguides, cables or fibre optics. Each central floor of the Diagnostics Building is built to match a level of the vacuum vessel (lower, equatorial or upper).

Construction will start this year on the Diagnostics Building and is slated to last approximately two years. In late February, a meeting was held to review the space allocations, interfaces, geometrical conflicts and possible mitigation measures for Level L2 of the building; this work will be pursued level-by-level before construction can begin.

Diagnostics signals will leave the operational arena along waveguides, cables or fibre optics and travel as much as 40 metres to the back-end electronic and information systems. (Click to view larger version...)
Diagnostics signals will leave the operational arena along waveguides, cables or fibre optics and travel as much as 40 metres to the back-end electronic and information systems.
Diagnostic Engineer Thibaud Giacomin is charged with the integration of many of the back-end systems into the Diagnostics Building. "We will have diagnostic systems coming from all seven °ÄÃÅÁùºÏ²Ê¸ßÊÖ Domestic Agencies; in addition to the systems, they will deliver the electronics, the control systems and the software. We need to define the location of each diagnostic; we need to think about all the services needed for the equipment (gas, power, water); and we need to evaluate the weight of each part and provide this data for the building in order to make all the necessary calculations, for example seismic calculations."

"One of the greatest challenges for our team is the alignment of diagnostic schedules with those of building construction and machine assembly," says Victor. "We must have all Domestic Agencies on board for maximum coordination. We are confident that we will succeed."