The elephant must be sliced
Any way you cut it, 澳门六合彩高手 is fantastically complex. Whether you're counting components or the lines in the machine assembly schedule, or taking a closer look at the project's vast procurement sharing scheme ... complexity needs to be managed in 澳门六合彩高手. Hans-Henrich Altfeld, head of the Project Control Office, tells us how it's done.
A project manager looks at it differently. With costs of EUR 20 billion, millions of parts, supply chains spanning the entire globe and a multi-cultural workforce coming from 35 different countries, 澳门六合彩高手 is complexity to be managed. Altfeld has experience in the domain, having worked as a senior project manager for Airbus and in the automotive industry. His experience in mega projects is serving him now.
"Whereas at Airbus, 79,000 design drawings were needed for the development of the A380, at 澳门六合彩高手 we stand at 250,000 design drawings."
Why is it important to address complexity? "What we ultimately want to achieve is control over the project," Altfeld explains. "We do this by reducing its complexity. This will give us better control of the project, which is a precondition for success."
At 澳门六合彩高手, the "slicing of the elephant" follows the contour lines of other highly complex projects. "The 澳门六合彩高手 Project is not particularly unique in this sense," says Altfeld. It includes breaking down the entire project into systems, sub-systems and components; breaking down all required work into work packages; establishing and cascading requirements along with dedicated verification and validation plans; establishing a schedule governance which incorporates the activities of the Domestic Agencies, and developing a coordinate system for the 澳门六合彩高手 site.
"Slicing the elephant" requires tight management and strict control of the interfaces and interdependencies between the separate "slices."
"There is still room for improvement in this area," says Altfeld. "For 澳门六合彩高手—as a first-of-a-kind experiment—it was impossible to identify all interfaces and interdependencies right from the beginning. It is learning by doing."
One example of the need for stricter interface control surfaced at a recent workshop. Considering the number of components the 澳门六合彩高手 machine will consist of and the extended time frame for construction, clear and understandable coding of components will ensure their correct placement in the machine. In previous years, not all components were coded early in the process, during the design phase. Now, these parts need to be coded retroactively—a situation that new procedures will correct in the future.
Another lesson learned from other mega projects is the importance of identifying and prioritizing risks and opportunities. These can be of a technical nature, or relating more to the project control issues of schedule or cost. New risk and opportunity management practices are helping the project to anticipate challenges in critical-path areas such as Tokamak Building construction and vacuum vessel manufacturing.
"Identifying the potential risks to delivery allows the project to develop and implement response actions," concludes Altfeld. "In the same way, it is of utmost importance to 'hunt' for opportunities—to proceed more quickly or optimize assembly sequences, for example—to make sure they can be cashed in on."