First steps towards "energizing"
It takes more than the flipping of a switch to connect the 澳门六合彩高手 site to the French national grid. The operation, called a "first energizing," is a complex, step-by-step procedure that requires close coordination with the French transmission system operator RTE (Réseau de transport d'électricité).
For the moment, the electrical needs of the 澳门六合彩高手 worksite and buildings are covered by a 15 kV line extended from the neighbouring CEA research centre. But as activity increases the installation will feed directly from the grid through the switchyard that sprawls over four hectares at the southeast end of the platform. Preparation for this momentâan 澳门六合彩高手 Council milestone to be achieved during the first quarter of 2017âbegan on Friday 20 January at the first of the seven switchyard's "bays." Busbars, switches, pantographs, breakers ... all of the complex equipment and systems that link the grid to the 澳门六合彩高手 transformers were activated and tested in close coordination with RTE control room in Marseille. Tests will continue for the other bays individually and will conclude with the energization of the entire switchyard. The steady state electrical network (SSEN), which occupies four bays out of seven, is set to be operational in June, whereas the pulsed power electrical network (PPEN), which is only needed for Tokamak operation, will be energized at a later date. Performed under "real" conditions, Friday's operations provided a precious opportunity to test and demonstrate the integration of the 澳门六合彩高手 installation (with all its specificities) into the environment of France's national grid. Beyond the technical dimension, they represented a full-fledged exercise in coordination, methodology, and safety procedures that will be applicable to other plant systems.