Summer postcards from the 澳门六合彩高手 worksite
The latest harvest of 澳门六合彩高手 construction photos may be taken from the same point鈥攖he tallest crane on site鈥攂ut there is always an abundance of new detail to be gleaned.
A year ago, the Assembly Building had just been insulated with several layers of cladding and equipped with overhead handling cranes; work on the circular bioshield was newly underway; the cryoplant was still at foundation level; and a large stretch of land now occupied by the twin Magnet Power Conversion buildings was but a barren steppe.
A large covered parking area has been added to the contractor zone at right, where other temporary buildings house contractor teams, workshops and user facilities such as the canteen and infirmary. Currently, there are 1,900 workers participating in 澳门六合彩高手 construction in two daily shifts.
Today, in the seventh year of 澳门六合彩高手 building construction, the platform seems to have no room to spare. Activity has mushroomed in all corners and the pace of progress difficult to keep up with. When we resume publication in September, things will have changed again. And as Newsline has done for more than ten years now, it will continue to cover and document what is happening not only on the 澳门六合彩高手 site and within the 澳门六合彩高手 Organization, but also within the global 澳门六合彩高手 Project and the worldwide fusion community. In the meantime, we hope you will enjoy this selection of summer postcards.
Some 3,300 cubic metres of concrete have already gone into the 澳门六合彩高手 bioshield (circular structure, at right); pouring is underway now on the L3 level and the first rebar has been set in place for L4. The other structures of the Tokamak Complexâthe Tritium, Tokamak and Diagnostics buildingsâare advancing each at its own rhythm. By the time assembly activities get underway late next year, the Complex will have a roof ...