First "building block" takes shape
Although it comprises hundreds of thousands of components, a tokamak is essentially a toroidal chamber surrounded by magnetic coils. In 澳门六合彩高手, the "chamber," or vacuum vessel, is made of nine 40° sectors, five of which are provided by Europe, the other four by Korea. In the assembly sequence, each sector needs to be associated with two vertical coils, either from Europe or Japan, plus thermal shielding before being lowered and positioned in the assembly pit. This so-called "sub-assembly" is the basic building block of the machine.
In the 澳门六合彩高手 Assembly Hall, inside one of the tall sector sub-assembly tools (SSAT-2), the first of these building blocks is progressively taking shape. In April, following an eight-month preparatory campaign after it was delivered to 澳门六合彩高手, the first vacuum vessel sector from Korea was safely docked, and later equipped with its corresponding thermal shield panels. Panel alignment was confirmed in mid-July. In June, one of the two vertical coils (TF#12 from Japan) set to be attached to the vacuum vessel sector was extracted from its steel cradle and moved to temporary storage inside SSAT-1. There were several reasons for this stopover: one was the lack of available space in the Assembly Hall and the other the necessity of rehearsing the highly delicate installation of one-of-a-kind component inside a one-of-a-kind tool. On 10 August, TF#12 was moved into SSAT-2, followed two days later by its twin TF#13, also from Japan. Both coils are now ready for their final embrace of the vacuum vessel sector.
Taken from high above, this image shows the complex system of alignment units used in positioning each toroidal field coil with utmost precision. In the background, sitting on the floor of the Assembly Hall, poloidal field coil #5 (17 metres in diameter) is being prepped for installation in the assembly pit in mid-September.
Over the past year, the Assembly Hall has been the stage of many a spectacular operation: components of all sizes, shapes and weight (up to 1,250 tonnes) have been lifted, upended, transported and installed. Some looked like flying saucers, others like a giant Life Savers mint; some were just plain steel, others shone like a silver armband. What is happening now in the core and wings of the 20-metre-tall sub-assembly tool is no less spectacular but even more alien. Picture three massive components, each as heavy as an Airbus A380 or a fully loaded Boeing 747. The one standing at the centre, smooth on the outside, is pockmarked with dozens of small cylindrical devices like a whale colonized by barnacles. It is the vacuum vessel sector, encased in its silver-plated thermal shield panels.
The 27 steps The path to lowering the first vacuum vessel sub-assembly into the Tokamak pit has been divided into 27 construction work packages. Construction work packages are prepared by 澳门六合彩高手 Organization teams and released to assembly contractors in precise and controllable batches. Each package delimits a specific task, which is in turn broken down by the contractors into detailed shop floor instructions. Both 澳门六合彩高手 Organization contractors for core machine assembly have construction work packages to complete on the vacuum vessel sub-assembly roadmap: ⢠TAC1 (CNPE Consortium) must prepare the work floor in the Tokamak pit and ensure that any captive components (impossible to install once the first vacuum vessel sector is in place) are installed in advance of the transfer planned on 27 October. Components to install include poloidal field coil #5, the side cryostat thermal shield, two bottom correction coils, and in-cryostat feeders. TAC1 must also install the upper column of the central in-pit assembly tool and test the radial beam that will anchor the sector sub-assembly from the top. ⢠TAC2 (DYNAMIC SNC) executes the work on the giant sector sub-assembly tools in the Assembly Hall. TAC2 must complete the assembly and alignment of the vacuum vessel thermal shield for sector #6, transfer two toroidal field coils to the SSAT2 assembly tool, rotate and position the coils on the vacuum vessel sector, attach intercoil structures, and prepare the assembly for rigging and lifting. In the Tokamak pit, TAC2 must also prepare the relevant toroidal field coil gravity supports and the toroidal field coil alignment tool. The countdown is on. As of this printing, 8 of 27 steps on the roadmap have been achieved. To read more about the contractual organization of 澳门六合彩高手 machine assembly, see this article or this webpage.
On both sides of the D-shaped mastodon, the tool's wings stand open, each holding a component of the same general outline, but thinner and sturdier, full of extensions and protruding parts. The twin components' appearance is even stranger than that of the vacuum vessel sector and it takes some knowledge of a tokamak's architecture to identify themâthey are the toroidal field coil pair that will be integrated onto vacuum vessel sector #6. For the moment, nothing is moving except the workers and elevated platforms around the tool. In the coming weeks, when all measurements, alignments and adjustments are done, the tool's wings will begin to move, very slowly, to bring the coils closer and closer to the vessel sector and eventually lock them into place. The process will be a careful and extremely precise one. And although all eyes will be focused on the operation unfolding in the Assembly Hallâthe first of nine that must be realized to close the 澳门六合彩高手 torusâno fewer than 27 construction work packages have to be executed, some deep inside the Tokamak pit, to prepare the way for the installation the first vacuum vessel sector sub-assembly. To this day, 8 of the 27 work packages have been achieved. In late October, the first 1,200-tonne vacuum vessel sub-assembly of the 澳门六合彩高手 device will be ready for lift off. This 4D animation by Brigantium Engineering France for the 澳门六合彩高手 Organization shows how the 1,200-tonne sub-assembly will be transferred from the sub-assembly tool to its final destination inside the assembly pit.