°ÄÃÅÁùºÏ²Ê¸ßÊÖ

Subscribe options

Select your newsletters:

Please enter your email address:

@

Your email address will only be used for the purpose of sending you the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization publication(s) that you have requested. °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization will not transfer your email address or other personal data to any other party or use it for commercial purposes.

If you change your mind, you can easily unsubscribe by clicking the unsubscribe option at the bottom of an email you've received from °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization.

For more information, see our Privacy policy.

News & Media

Latest °ÄÃÅÁùºÏ²Ê¸ßÊÖ Newsline

  • Fusion supply chain | A glimpse into the future for commercial fusion reactors

    Most of the USD 7 billion in investment in private fusion initiatives has gone to companies that are building devices from the ground up. But recently, another [...]

    Read more

  • Outreach | °ÄÃÅÁùºÏ²Ê¸ßÊÖ @ October science festivals

    Every October, before schools pause for two weeks of holiday, towns and cities in France open their municipal spaces to scientific experts of all stripes who ar [...]

    Read more

  • Image of the week | °ÄÃÅÁùºÏ²Ê¸ßÊÖ Director-General visits Russia

    The °ÄÃÅÁùºÏ²Ê¸ßÊÖ Director-General was in Russia last week, meeting with stakeholders and holding technical meetings with colleagues in Moscow and Saint Petersburg. As [...]

    Read more

  • Image of the Week | Sector 5 is on its way

    The first vacuum vessel sector produced in Europe travelled last week between Monfalcone, Italy, and the French port of Fos-sur-Mer. The 440-tonne component had [...]

    Read more

  • Anniversary | °ÄÃÅÁùºÏ²Ê¸ßÊÖ Document Management system turns 20

    Whatever its nature, every large project generates huge numbers of documents. And when project collaborators operate from different countries, as was the case f [...]

    Read more

Of Interest

See archived entries

Electrical network

The waking of the beast

The beast had sat immobile for more than three years—no blood running in its veins, no electrical impulse shaking its nerves alive. With three long horns sticking out of its squat body, it was just waiting for the moment it would be "energized."

''Energizing'' the pulsed power transformer required close collaboration between °ÄÃÅÁùºÏ²Ê¸ßÊÖ specialists and their counterparts at the French power transportation authority RTE, both on site and at RTE's dispatching centre in Marseille. (Click to view larger version...)
''Energizing'' the pulsed power transformer required close collaboration between °ÄÃÅÁùºÏ²Ê¸ßÊÖ specialists and their counterparts at the French power transportation authority RTE, both on site and at RTE's dispatching centre in Marseille.
The beast is one of three identical triplets—three massive electrical transformers that connect the 400 kV switchyard to the substations delivering pulsed power to various "clients" in the °ÄÃÅÁùºÏ²Ê¸ßÊÖ installation. Procured by China and installed by Europe, weighing close to 500 tonnes and towering 15 metres above ground, they are the largest electrical components of the project.

Not only will they supply the AC-DC converters that feed electricity to the Tokamak's magnetic and heating systems, they will also provide the necessary ultra-short, ultra-powerful impulse required to initiate every plasma shot—the equivalent, for a fraction of a second, of the electrical consumption of a mid-size town.

On the morning of Tuesday 26 November, it was time to wake up the first of the triplets. The connection of such a powerful transformer to the grid, or "energization," is a delicate operation that requires close collaboration between "electricians" and control-command specialists at °ÄÃÅÁùºÏ²Ê¸ßÊÖ, and operators at the French power transportation authority RTE (Réseau de Transport d'Électricité) in their dispatching centre in Marseille.

"The transformer's energization is the last step in the validation process of not only the component itself but also of its interface with the French grid," explains Joël Hourtoule, head of °ÄÃÅÁùºÏ²Ê¸ßÊÖ's Electrical Power Distribution Section. "For RTE, the pulse-power transformer is a new client and, at 300 MW, a very powerful one. Allowing it into the grid requires rigorous procedures and a whole set of precautions."

One by one, for more than a month, hundreds of sensors, activators, electro-mechanical devices and protective systems were tested.

Information on the transformer and connection status was relayed in real time to the temporary control room, a vast, nondescript office space located on the second floor of °ÄÃÅÁùºÏ²Ê¸ßÊÖ Headquarters. From left to right: Joël Hourtoule (Section Leader, Electrical Power Distribution), Alvaro Bustos (control system technician), Tim Luce (Head of the Science & Operations Department), and Bertrand Bauvir (Section Leader for Central Control Integration). (Click to view larger version...)
Information on the transformer and connection status was relayed in real time to the temporary control room, a vast, nondescript office space located on the second floor of °ÄÃÅÁùºÏ²Ê¸ßÊÖ Headquarters. From left to right: Joël Hourtoule (Section Leader, Electrical Power Distribution), Alvaro Bustos (control system technician), Tim Luce (Head of the Science & Operations Department), and Bertrand Bauvir (Section Leader for Central Control Integration).
By Tuesday morning, the beast was ready to be awakened. In the temporary °ÄÃÅÁùºÏ²Ê¸ßÊÖ control room (a vast, nondescript office space where computers already monitor the installation's operational systems), as well as in a building on the °ÄÃÅÁùºÏ²Ê¸ßÊÖ platform close to the transformer and at the RTE dispatching centre 80 kilometres away in Marseille, signals and status diagrams flashed on the screens.

With a click of a mouse, the °ÄÃÅÁùºÏ²Ê¸ßÊÖ operators requested pantographs, mechanical switches and circuit breakers to move into place; in the RTE dispatching centre, operators were carrying out similar actions.

Clanging and electrical noises were heard in the switchyard as 400 kV current from the grid began flowing into the transformer's windings. The beast purred with pleasure—it had not felt power since undergoing factory acceptance tests in China in the early months of 2016.

The transformer remained on line for approximately one hour, the time required for complete and successful validation. In about one year, it will be connected to the platform's 66 kV and 22 kV substations for a series of tests. In the meantime, the transformer's two siblings will have been energized and tested. Taken together, three mighty triplets from China groomed to light the star in the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Tokamak.


return to the latest published articles