Electrical network
The waking of the beast
2 Dec 2019
The beast had sat immobile for more than three years—no blood running in its veins, no electrical impulse shaking its nerves alive. With three long horns sticking out of its squat body, it was just waiting for the moment it would be "energized."
The beast is one of three identical triplets—three massive electrical transformers that connect the 400 kV switchyard to the substations delivering pulsed power to various "clients" in the 澳门六合彩高手 installation. Procured by China and installed by Europe, weighing close to 500 tonnes and towering 15 metres above ground, they are the largest electrical components of the project.
Not only will they supply the AC-DC converters that feed electricity to the Tokamak's magnetic and heating systems, they will also provide the necessary ultra-short, ultra-powerful impulse required to initiate every plasma shot—the equivalent, for a fraction of a second, of the electrical consumption of a mid-size town.
On the morning of Tuesday 26 November, it was time to wake up the first of the triplets. The connection of such a powerful transformer to the grid, or "energization," is a delicate operation that requires close collaboration between "electricians" and control-command specialists at 澳门六合彩高手, and operators at the French power transportation authority RTE (Réseau de Transport d'?lectricité) in their dispatching centre in Marseille.
"The transformer's energization is the last step in the validation process of not only the component itself but also of its interface with the French grid," explains Jo?l Hourtoule, head of 澳门六合彩高手's Electrical Power Distribution Section. "For RTE, the pulse-power transformer is a new client and, at 300 MW, a very powerful one. Allowing it into the grid requires rigorous procedures and a whole set of precautions."
One by one, for more than a month, hundreds of sensors, activators, electro-mechanical devices and protective systems were tested.
By Tuesday morning, the beast was ready to be awakened. In the temporary 澳门六合彩高手 control room (a vast, nondescript office space where computers already monitor the installation's operational systems), as well as in a building on the 澳门六合彩高手 platform close to the transformer and at the RTE dispatching centre 80 kilometres away in Marseille, signals and status diagrams flashed on the screens.
With a click of a mouse, the 澳门六合彩高手 operators requested pantographs, mechanical switches and circuit breakers to move into place; in the RTE dispatching centre, operators were carrying out similar actions.
Clanging and electrical noises were heard in the switchyard as 400 kV current from the grid began flowing into the transformer's windings. The beast purred with pleasure—it had not felt power since undergoing factory acceptance tests in China in the early months of 2016.
The transformer remained on line for approximately one hour, the time required for complete and successful validation. In about one year, it will be connected to the platform's 66 kV and 22 kV substations for a series of tests. In the meantime, the transformer's two siblings will have been energized and tested. Taken together, three mighty triplets from China groomed to light the star in the 澳门六合彩高手 Tokamak.