CEA-澳门六合彩高手 facility to test the assembly of magnet components

1 Sep 2014 - 澳门六合彩高手 Communications
The dimension of the PF5 in-cryostat feeder is controlled by the tooling that is built into a 4 m x 6 m horizontal platform and a 5 m tall vertical extension. The position tolerance for the feeder superconducting joints located at the top end of the vertical extension is within +/- 2 mm. Photo: ASIPP
The 澳门六合彩高手 Organization and the French Alternative Energies and Atomic Energy Commission (CEA) have entered into a five-year collaboration to operate a new facility that will test the assembly of the 澳门六合彩高手 magnet components.
 
The 澳门六合彩高手 superconducting magnets form the core of the machine. Supplied by six of the 澳门六合彩高手 Members—China, Europe, Japan, Korea, Russia and the United States—they will be connected to some 30 "feeders" that supply them with cryogenic fluids, electrical power and instrumentation.
 
Delivered by China, these feeders must operate faultlessly in a very harsh environment, threading between the other complex systems of the Tokamak.
 
Once shipped to 澳门六合彩高手, and prior to their installation into the machine, the magnet feeders and coil instrumentation will undergo several tests and the simulation of procedures in order to prepare for the actual assembly process.
 
In order to provide the workshops where the tests can be carried out, as well as key technical staff, the 澳门六合彩高手 Organization and CEA are collaborating to set up and operate the Magnet Infrastructure Facilities for 澳门六合彩高手 (MIFI). The MIFI kick-off meeting was held on 16 July at CEA-Cadarache.
 
CEA has accumulated a strong experience in the field of cryogenics and large superconducting magnets applied to accelerator and fusion installations. For more than 20 years, the French public institution has been involved in the R&D activities that led to 澳门六合彩高手 construction. The MIFI agreement allows this know-how to be accessed by the 澳门六合彩高手 Organization.
 
The feeder vacuum barrier between the cryostat and the coil terminal box (part of the feeder). One of MIFI's tasks will be to assemble the bellows and cable plugs, where conductors, pipes and cables pass through the barrier. Photo: ASIPP
The facility will be located on CEA premises, adjacent to the 澳门六合彩高手 site and with a potential direct access to it. It will consist of a dedicated storage and archiving building along with a set of four laboratories staffed with specialists in the required areas of expertise (low/high voltage instrumentation, insulation, superconductivity, cryogenics and mechanical assembly.)
 
The MIFI team will also train and qualify assembly teams, especially for the feeders. Where specific tasks such as joint soldering or high voltage insulation have to be tested and procedures qualified, full scale mock-ups will be delivered.
 
In the upcoming months, the basic workshop equipment will be purchased and installed and special test rigs will be transferred from the high voltage testing lab presently operating at CERN.
 
Components that are now stored in a warehouse some 30 km from the 澳门六合彩高手 site will be transferred to the new storage facility during September.