A colossal task made manageable
For the execution of work during the next project phase—machine and plant assembly up to First Plasma—the 澳门六合彩高手 Organization has chosen a contractual approach that emphasizes manageably sized work packages with strong risk management. Nine major assembly and installation contracts are foreseen.
- Strive for cost and schedule control and flexibility through manageable lots;
- Minimize interference and interfaces between the different contractual scopes;
- Secure timely work execution by foreseeing temporary backup;
- Benefit from industry knowledge and know-how wherever possible;
- Allow industry to propose methods or processes within well-defined boundaries to accelerate or optimize work.
Within these zones, work will be executed under nine major assembly and installation contracts.
"We have chosen to divide the assembly scope into manageable work packages with time phasing and clear responsibility for performance in order to permit better schedule and cost control throughout the lifetime of the contracts," says Katsumi. "This approach will give us the flexibility we need to work with uncertainty—either in the effective handover dates of certain work zones, the availability of tooling, or the risk that some components may be delayed or require adjustment on arrival."
Time phasing means that work will be carried out based on construction work packages that are released by the 澳门六合彩高手 Organization in achievable—and trackable—batches. In some cases, contractors will be involved in the engineering development of the work packages to provide early input on construction optimization and methodology.
For the most complex and time-sensitive areas—the Tokamak machine and the Tokamak Complex—the choice has been made to preserve peer competition by splitting the works in these areas between at least two contractors. It also protects the 澳门六合彩高手 Organization in the case of contract default, as one contractor can take over in a relatively short amount of time from the other.
Contracts are awarded through competitive call for tender. First, the 澳门六合彩高手 Organization invites companies from the 澳门六合彩高手 Members to express interest through the "Call for Nomination" process. This stage is followed by a pre-selection of candidate tenderers (the "Pre-Qualification Application"), and finally the tender invitation is effectively issued ("Call for Tender"). (See more about the 澳门六合彩高手 procurement process here.)
The global tendering phase for the assembly and installation contracts is now drawing to a close. All Balance of Plant contracts have been issued; the two Tokamak Assembly (TAC) contracts have been awarded (but not yet signed); and the two Tokamak Complex (TCC) tenders are under evaluation.
The 澳门六合彩高手 Newsline will have a full report on contract awards in September.