Three more segments for the cryostat
27 Jun 2016
One by one the elements that make up the base of the 澳门六合彩高手 cryostat—the single largest load of Tokamak assembly—are being delivered to the 澳门六合彩高手 site from India and safely stored in the Cryostat Workshop.
Twelve segments were in December 2015 for tier 1 of the 1,250-tonne base section. Three further segments, weighing approximately 120 tonnes each and representing half of the elements needed to assemble tier 2, arrived at 澳门六合彩高手 in the early hours of Friday 24 June.
Work will begin this week on the assembly of the first support and transport frame—one of a set of three large steel structures that will support components, jigs and fixtures during the cryostat assembly process. The 30 x 30 metre frames will also act as transporters for the completed cryostat sections.
By mid-July, the welding machines should be installed in the Cryostat Workshop in time for welding operations to begin in August.
The final three segments of the cryostat base are scheduled for delivery in the first week of September.