First machine components safely stored

In December, the first 12 segments of the massive °ÄÃÅÁùºÏ²Ê¸ßÊÖ cryostat were delivered to the °ÄÃÅÁùºÏ²Ê¸ßÊÖ site in Saint-Paul-lez-Durance, France. 
Cryostat_segment_milestone_1_small.jpg
The 12 segments, forming the first tier of the cryostat base section, are now stored in the Cryostat Workshop. Welding operations will begin in the summer of 2016.
The 3,850-tonne cryostat, the vacuum-tight container that will surround the main plasma chamber and superconducting magnets, is under the procurement responsibility of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ-India Domestic Agency and manufactured by the Indian industrial giant Larsen & Toubro Ltd.
 
The arrival of the cryostat segments represents a double milestone for the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Project—the arrival of the first elements that will be integrated into the °ÄÃÅÁùºÏ²Ê¸ßÊÖ machine, and the ahead-of-schedule achievement of the first project milestone validated by the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Council in November for the years 2016-2017.
 
Read the press release in English and in French.