Tokamak assembly
The size and weight of the major components, the tiny tolerances and careful handling required for the assembly of huge and unique systems, the diversity of manufacturers, the tight schedule, complex interfaces ... all of these elements combine to make the assembly of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ tokamak an engineering and logistics challenge of enormous proportions.
Core machine assembly is proceeding from bottom to top. Beginning with the heaviest single component—the 1,250-tonne cryostat base, installed in May 2020—assembly contractors are executing the sequence as planned: lower poloidal field coils, cryostat lower cylinder and thermal shield and, over the next years, the nine vacuum vessel modules, subsequent ring coils, components at the top of the machine, central solenoid and, finally, the cryostat lid.
1
Components enter the Assembly Hall through the Cleaning Facility, where they are unpacked and cleaned with compressed air, pressurized demineralized water, or specialty detergents. The Cleaning Facility operates as an airlock between the Hall and the outside environment.
2
The overhead crane system transfers the newly arrived loads to temporary laydown areas, or zones reserved for sub-assembly activities. Then, in the order determined by assembly sequences, the components or assemblies are transported to the Tokamak pit, a 30-metre-deep concrete cylinder in the centre of the Tokamak Building.
3
The °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization is using a number of other warehouse spaces on site to receive, inspect and prepare the largest components for handling in the Assembly Hall. Each °ÄÃÅÁùºÏ²Ê¸ßÊÖ component is absolutely unique—and in many cases has required ten years to design, prototype and manufacture. Every possible precaution is taken in their unloading and transport.
4
Contractors working under the supervision of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization are carrying out the thousands of complex lifting, positioning, joining, and inspection activities of °ÄÃÅÁùºÏ²Ê¸ßÊÖ machine assembly.
These contractors are carrying out the day-to-day work of machine assembly under the oversight of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization:
Tokamak in-cryostat assembly
The CNPE Consortium (China Nuclear Power Engineering; China Nuclear Industry 23 Construction Company Ltd.; Southwestern Institute of Physics; Institute of Plasma Physics, Chinese Academy of Sciences ASIPP; and Framatome) is responsible for tokamak machine assembly (assembly of the cryostat and cryostat thermal shield; magnet feeders; the central solenoid, poloidal field and correction coil magnets; and cooling structures and instrumentation).
Vacuum vessel assembly
The CNPE Consortium is responsible for Sector Module Sub-Assembly, SMSA (assembly of the vacuum vessel sectors with toroidal field coils and vacuum vessel thermal shielding). In partnership with SIMIC S.p.A., the CNPE-Consortium is also executing the contract for Sector Module Assembly in Pit, SMPA (aligning and using intercoil structures to connect the nine sector modules in the pit).
Vacuum vessel & port welding
The °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization is in the process of finalizing a negotiation with the multinational company Westinghouse for vacuum vessel welding (production phase in the tokamak pit). In the meantime, in order to develop and finalize the correct technologies and processes to be used, a contract covering welding process qualification (engineering and qualification of all processes and new tools required for nine-sector simultaneous welding) was placed with the company in September 2024. The Indian firm Larsen & Toubro has been awarded a contract for port positioning alignment and welding (engineering, qualification and tools and in-pit welding of vacuum vessel ports and bellows).
23,000
tonnes
1,000,000
components
1,200
engineering packages
10
years
°ÄÃÅÁùºÏ²Ê¸ßÊÖ by drone, October 2024 (subtitle version)
A four-day "reverse lift"
Robots welding the °ÄÃÅÁùºÏ²Ê¸ßÊÖ vacuum vessel (ENSA)
Manipulator arms: super strong and ultra precise
Going deeper and deeper into virtual reality
Tokamak assembly: The module has landed
Preparing for the Big Lift
Installing a 40° section of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ vacuum vessel (Brigantium Engineering)
Metrology-assisted assembly at the °ÄÃÅÁùºÏ²Ê¸ßÊÖ nuclear fusion project (Hexagon)
Machine Assembly
Bringing a vacuum vessel sector into tooling
Major lift to assembly tooling (Ortec)
First ring-shaped coil produced on site is positioned in assembly pit
First vacuum vessel sector safely docked
Time-lapsing through machine assembly (May 2020-March 2021)
Largest tokamak component installed
4D: Cryostat base lift
°ÄÃÅÁùºÏ²Ê¸ßÊÖ NOW 1.11: The Big Lift
First machine component installed
Assembly challenges
Alignment
Accurate alignment, particularly of the magnet system and in-vessel components, is essential to the successful operation of the machine. Dimensional control is critical to ensuring that tolerances are respected, and to recording the "as-built" status of the machine, which will be directly compared against °ÄÃÅÁùºÏ²Ê¸ßÊÖ's Computer-Aided-Design (CAD) models in order to correct eventual deviations in alignment before they accumulate. Positional tolerances for the largest components, including the magnet coils and the vacuum vessel, are as low as 2 mm. (For more information, see Metrology.)
Ultra-high and high vacuum
°ÄÃÅÁùºÏ²Ê¸ßÊÖ will host one of the largest and the most complex high vacuum systems ever built. To ensure correct machine performance, all connections associated with ultra-high vacuum or high vacuum components must be 100 percent leak-tight. Vacuum lines, helium lines, pipes, valves, seals, joints, and/or flanges have all gone through pre-qualification, while some of the largest vacuum components—for example, the seals manufactured for the vacuum vessel‘s 50+ large ports—are being tested on dedicated test rigs. For in-pit assembly, only qualified welding procedures, carried out by certified professionals, are employed, and the quality of all vacuum-related welds is verified by surface and volumetric non-destructive examination. Full-scale leak testing is planned during the integrated commissioning period before the Start of Research Operations, in which the large vacuum chambers—the vacuum vessel and the cryostat—are evacuated and leak tested. In parallel, the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization is developing a set of specialized tools and technologies for the localization and detection of leaks smaller than the width of a human hair divided by one million.
Logistics
The °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization and its assembly partners are managing a large volume of assembly activities—such as major lifting operations, handling/positioning, mechanical fixation, welding, cabling, pipe work, metrology, non-destructive examination, and leak testing—all in the extremely crowded environment of the Tokamak pit and the Tokamak Complex. Close coordination between assembly contractors and supervision teams is crucial.
Vacuum vessel welding
Welding the °ÄÃÅÁùºÏ²Ê¸ßÊÖ vacuum vessel and ports inside of the assembly pit will require several years, a large skilled team, and a host of customized techniques and tools. The welding tools will have to manoeuvre the complex geometry of the sectors and ports and reach areas that are not directly accessible to operators and where visibility is restricted. The robots will also be confined to welding from inside the vessel and ports, as the pre-installed vacuum vessel thermal shield makes access to the exterior surfaces impossible. Extensive trials on mockups have been performed to quantify and plan for shrinkage and deformation, and to qualify tools, processes, and inspection techniques.
French nuclear regulations
As the nuclear operator of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ installation, the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization has an obligation to ensure that safety and security standards are implemented and enforced throughout construction, manufacturing, assembly, and operation in compliance with the Host country's safety and security regulations. All activities related to a safety-important or protection-important component or system (for example °ÄÃÅÁùºÏ²Ê¸ßÊÖ's first confinement barrier, the vacuum vessel) must be performed correctly and documented as verified through regular surveillance and inspection.
Interfaces
Once delivered to the site, the interfacing elements for a number of large components such as the °ÄÃÅÁùºÏ²Ê¸ßÊÖ blanket and the divertor have to be customized to comply with precise alignment requirements. Assembly contractors will have to use dimensional control and reverse engineering to plot out this customization, and must provide the workshop space, tooling and expertise to carry out the work on short timescales.
Schedule
Throughout Assembly Phase I, the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization will rely heavily on the on-time delivery of components and systems from the seven Domestic Agencies. Any delay related to fabrication or transport risks disrupting the carefully planned assembly sequences, especially for time-critical components such as the magnets or the vacuum vessel sectors.