First magnet in place
When it travelled the 澳门六合彩高手 Itinerary last year, or during cold tests in the onsite winding facility, poloidal field coil #6 (PF6) felt rather large and massive. Although only 10 metres in diameter—compared to 24 metres for the largest of the six ring coils that circle the machine—the 330-tonne coil is particularly thick and bulky. But everything is relative. On Thursday 21 April when the coil was extracted from its support frame and lifted 25 metres overhead to be transferred to the assembly pit, the perception of its size changed dramatically: dwarfed by the huge volume of the Hall, it suddenly felt small—a steel frisbee slowly gliding through immensity.
PF6 is a European procurement that, for organizational reasons, was manufactured in China by the Institute of Plasma Physics of the Chinese Academy of Sciences (ASIPP). "The problem we faced was that the first two coils to be installed, PF6 and the much larger PF5, had to be delivered at almost at the same time," explains Alessandro Bonito-Oliva, the Magnets Programme Manager at the European Domestic Agency Fusion for Energy. "As there was not enough space in the on-site winding facility to install two parallel production lines we discussed the issue with different Domestic Agencies and eventually determined that ASIPP was the best potential supplier."
The coil shipped from Hefei by barge in March 2020, sailed the Yangtze River to Shanghai, and reached the French port of Fos-sur-Mer in June. In order to allow for transport to the 澳门六合彩高手 construction site, a few portions of the 澳门六合彩高手 Itinerary had to be adapted or enlarged.
The lifting, handling and installation of PF6 on 21 April 2021 was an eight-hour operation that required a complex rigging system capable of rotating the coil and positioning it to within 4 millimetres of tolerance. Composed of a 92-tonne dual crane heavy load beam (also used to lift the first vacuum vessel sector), a 42-tonne lifting frame, and a set of lifting adapters, the rigging brought the total load to approximately 480 tonnes—the third heaviest lift after the cryostat base and vacuum vessel sector #6, transported in May 2020 and April 2021 respectively.
On the day before the operation the team performed a lift test, and assessed the risk of not compensating the slight imbalance in the component's centre of gravity caused by a one-tonne feeder interface that sticks out from under the coil on one side. "The slight tilting of the coil during the lift did not exceed one degree and remained within tolerance," explains Jens Reich, the head of the Ex-Vessel Delivery & Assembly Division, as the coil settled on its supports in the late afternoon. "Everything went perfectly smoothly."
PF6 will remain on its temporary supports for a few years, pending the installation and welding of all nine vacuum vessel sub-assemblies. Once this is completed, the hydraulic system of the temporary supports will slightly lift the coil to anchor it to the toroidal field coil superstructure. A similar sequence will be followed for the next poloidal field coil (PF5, 17 metres in diameter), which is due inside the pit this summer.
See a report on the Fusion for Energy .