Furnishing and finishing
This week, furnishings were moved into the new temporary office building that has been erected adjacent to °ÄÃÅÁùºÏ²Ê¸ßÊÖ Headquarters. The handover of this new building—JWS3—will take place this coming Monday, 31 May. A pedestrian pathway now exists on the worksite between the guard station and the sub-contractors area allowing staff members who choose to walk this distance in all security instead of taking their car.
Close to the water-treatment installations, work continues to create a waste management area where garbage recycling containers will be stored. The installation of electrical networks and resurfacing began this week and should be completed by the end of the month.