With work beginning on the ground level (L1) of the Diagnostics Building, the concrete and steel of the Tokamak Complex will soon be flush with the °ÄÃÅÁùºÏ²Ê¸ßÊÖ platform. The 90 x 130 metre "Pit" of yesterday is gone but the central, perfectly round assembly area for the Tokamak remains ...
Pit_General_1_small.jpg
In the centre of the Tokamak Complex worksite, 6 concrete plots out of 11 have been poured for the Tokamak Building's B1-level basemat, as well as 6 massive columns out of 18. Pouring and rebar installation continues for successive levels of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ bioshield, the 3.2-metre-thick "ring fortress" surrounding the machine whose role is to protect workers and the environment from the radiation generated by the fusion reaction.
 
Pit_Clouds_Workers_small.jpg
The landscape in the area is now dominated by the black, temporary facade of the Assembly Building, now adorned with a giant poster of the °ÄÃÅÁùºÏ²Ê¸ßÊÖ machine. Eventually, as the Tokamak Building rises to meet the Assembly Building, the cladding will be removed and the two buildings will be joined into one.