Rock blasting is nearing completion
Tokamak Complex excavation and support structure:
Ongoing rock blasting and excavation is continuing in the area of the future Tokamak Complex. The first phase of blasting is nearing completion.
Poloidal field coil fabrication building:
Concrete slab pours are continuing. In tandem, concurrent activities are progressing westwards along the building, including work on the column footing installation, concrete column reinforcement and cast-in-place concrete placement is continuing for the above-ground structure.
Permanent °ÄÃÅÁùºÏ²Ê¸ßÊÖ Headquarters ('Annex Buildings'):
Concrete placement work has begun for the foundation at the west end of the building for the future permanent °ÄÃÅÁùºÏ²Ê¸ßÊÖ Headquarters buildings. Ground foundation anchors and other ground preparation works are continuing.
Site infrastructure:
Authorization to access the on-platform water supply and on-platform electrical power has been achieved for use in one of the first major building construction contracts (Poloidal Field Coils Winding Facility).