澳门六合彩高手

Spring is blooming, construction is booming

In a scene reminiscent of an Apollo Moon mission, geologists take measurements in the Tokamak excavation pit.
It is springtime on the 澳门六合彩高手 site. Green is sprouting along the embankments, and construction, in Tim Watson's own words, "is progressing reasonably well" both on the platform and just below, on the Headquarters Building worksite.
 
"Everything is going pretty much as planned," says the Head of the Buildings & Site Infrastructure (BSI) Directorate. Concrete structures in the basement level of the future 澳门六合彩高手 Headquarters are now nearing completion and work on the ground floor, where the social amenities such as a restaurant and bank counter will be located, is now well underway.
 
A "model office" should be set up in September 2011 to test the layout of furniture and office equipment. The 澳门六合彩高手 Headquarters will accommodate some 500 澳门六合彩高手 staff in a set-up designed as "a good balance between very large open-plan offices and small single occupancy offices." Agence Iter France and the European Domestic Agency F4E are expected to hand the building over to the 澳门六合彩高手 Organization during the summer of 2012.
 
A "fairly conventional construction, but a very big one," the Poloidal Field Coil Assembly Building has entered "roof and cladding" operations.
On top of the 澳门六合彩高手 platform, Tokamak excavation works (literally) reached rock bottom last month. By way of radar mapping and the boring of more than 500 holes, geological surveys provided a detailed map of the substratum. Some voids were detected, the largest being a few cubic meters in volume; these voids will now be filled with concrete.
 
The Tokamak excavation area is now being readied for the pouring of a thin layer of 'blinding concrete' that will create the clean and flat work surface upon which the 1.5-metre-thick "lower basemat" will be created. Concrete operations should begin a few weeks from now and last until the end of the year. Some 82,000 tonnes of concrete will go into the lower basemat alone.
 
A "fairly conventional construction, but a very big one," the Poloidal Field Coil Assembly Building has entered "roof and cladding" operations. Five out of the six poloidal field coils of the 澳门六合彩高手 Tokamak will be assembled here; operations could begin as early as 2012 and last until 2017.
 
What will happen to this 11,000 square metre building once coil winding operations are complete? "Everybody wants to use it," says Tim. "Nothing has been decided yet, but people always use a space if it's there... There are indeed lots of things you can do in a large open space with two cranes."
 
An artist's view of the 4,000 square metre "switchyard" through which power will be fed to 澳门六合彩高手. ? AIF
A new and quite large element, in the form of a 43-metre-high electricity pylon, will soon be added to the platform scenery. The pylon will be anchored between the "green" and "blue" buildings of the present contractors' area, and will support the last portion of the 400 kV lines destined to supply current to the 澳门六合彩高手 installation. In June, France's electricity carrier RTE (Réseau de Transport d'?lectricité) will commence the construction of the large (40,000 square-metres) "switchyard" through which power will be fed to 澳门六合彩高手.
 
What has been accomplished since last August is impressive. It was only nine months ago, after all, that bulldozers, scrapers and power shovels returned to the 澳门六合彩高手 platform.