澳门六合彩高手

An update on 澳门六合彩高手 construction

13 Nov 2009 - Timothy Watson, Deputy Head of the CCS Office
JWS 3, which should be completed in June 2010, will be home to 200 staff from the European Domestic Agency and 100 staff from 澳门六合彩高手.

Following the conceptual design review of all 澳门六合彩高手 buildings and site infrastructure which took place in February 2009, the CCS Office has been busy preparing updated final functional requirements, ready for the European Domestic Agency to pass onto its selected architect engineering contractor. The European agency has been busy with the procurement not only of its architect engineer, but also of ancillary services such as owner support and the independent health and safety coordinator that is required under French law.

The final functional requirements consist of system requirements documents, system description documents, and interface control documents as well as the detailed and the configuration models for the buildings. In all, more than 350 documents are now being made available to the European Domestic Agency and its contractors.

Once the architect engineering contract is in place, the European agency will be able to move forward with the detailed design of all the buildings and site infrastructure. Tenders are currently being analyzed, and it is hoped that this can be completed quickly in order for the selected company to begin work early in 2010.

The first building to be completed on site will be the winding facility for 澳门六合彩高手's poloidal field coils. The Procurement Arrangement for this building was signed with Europe in November 2008, and construction is planned to start mid-2010. Excavation of the Tokamak Pit is also planned to begin around this same date, if the excavation procurement process is completed on schedule in early 2010.

Adjacent to the main platform, the annex buildings—including the future 澳门六合彩高手 offices—are in the process of being rationalized with French and European commitments being merged together to ensure 澳门六合彩高手 minimum requirements are met. The welcome and communication services that were originally planned as independent buildings will be incorporated into the main office building, allowing closer integration of the overall 澳门六合彩高手 team. The tendering process for the annex buildings has been launched and it is expected that the two-year construction works will commence in the middle of 2010—good news for us all!

Visible progress is being made just outside of Headquarters as the preparatory works for the twin temporary office building JWS 3 move ahead. This building will be home to 200 staff from the European Domestic Agency and 100 staff from 澳门六合彩高手. It is expected that the building will be completed in June 2010.

While the period of low visible activity on the 澳门六合彩高手 construction site is likely to continue through the initial months in 2010, it is anticipated that if Europe can maintain the momentum of its current procurement activities, then by the middle of next year, building works will have begun in earnest. From this point forward, building will be a daily physical reminder of the progress being made on the 澳门六合彩高手 Project.