°ÄÃÅÁùºÏ²Ê¸ßÊÖ

Work on site progressing

31 Mar 2008 - Sylvie André, Agence °ÄÃÅÁùºÏ²Ê¸ßÊÖ France

The work on the °ÄÃÅÁùºÏ²Ê¸ßÊÖ construction site is progressing rapidly, the landscape changing from day to day. Already installed are the portacabins for the workers and subcontractors. The next step is the construction of the 300 new temporary offices for the °ÄÃÅÁùºÏ²Ê¸ßÊÖ team which will be ready by October this year. They will be located behind the Extension II on the other side of the fence. A pedestrian gate will allow access to the site. The preparatory work for the 3700 m platform and the electrical installations, telephone, internet lines etc. is underway.

Furthermore, Agence °ÄÃÅÁùºÏ²Ê¸ßÊÖ France together with the CEA Cadarache are currently installing the power supply for the new °ÄÃÅÁùºÏ²Ê¸ßÊÖ offices and the new car park. For that, the 15 kV line coming from Tore Supra will be reduced to a 400 Volt line.