In the coming months, after a large door is created in the north wall facing the cryoplant, the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization will use the space previously occupied by the
coil winding table and adjacent work station to proceed with
thermal shield repairs. Later this year, in September, a second partial handover will extend the Organization's "exclusive area" to about half of the facility's space. In this newly acquired territory, °ÄÃÅÁùºÏ²Ê¸ßÊÖ will set up the
port plug test facility, whose components will arrive from Russia. By mid-2024, after the final coils PF4 and PF3 have been delivered and all coil-related activity has ended, a final handover will give the °ÄÃÅÁùºÏ²Ê¸ßÊÖ Organization complete ownership of the building. At the far end, where the concrete slab can withstand pressures on the order of 42 tonnes per square metre, °ÄÃÅÁùºÏ²Ê¸ßÊÖ will conduct
divertor cassette assembly operations and other heavy-duty activities.