澳门六合彩高手

Twin giants to pre-assemble the vacuum vessel

4 Mar, 2024

As the doors of the Assembly Building open to admit the first vacuum vessel sectors shipped from manufacturing sites in Europe or Korea, two imposing custom-built tools will stand ready to receive them.

Section lifting tool
Six storyes high, made of 800 tons of steel, the Sector Sub-Assembly tools will work in concert to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit.

Six storyes high, with wings spreading 20 metres, the Sector Sub-Assembly tools will work side by side to equip the nine sectors of the vacuum vessel before their transfer to the Tokamak Pit, where they will be welded together to form the torus-shaped 澳门六合彩高手 vacuum chamber.

"It's far from a simple operation," says Emma Watson, an engineer who works within the Machine Assembly & Installation Section at 澳门六合彩高手. "For each of the nine sectors, the complete sub-assembly operation will take five to six months." To optimize the overall schedule for the nine sectors, two identical tools are planned, each one capable of holding a sector on its end while positioning—and aligning—the associated components.

The sectors, which will travel from the factories in a horizontal position, will first have to be "upended" by a dedicated tool that is designed to lift the 440-ton (max) vacuum vessel sectors (7.6 x 6.5 x 13.7 metres) and the 310-ton toroidal field coils (9 x 3.7 x 17 metres) into their final, vertical orientation.

Then the Sector Sub-Assembly tools will take over, suspending each vacuum vessel sector from the top while carefully positioning and installing—via the rotary motion of the "wings"—the vacuum vessel thermal shields and two toroidal field coils. The sub-assemblies will be maintained in place as the remainder of the operations that must be completed on each 40° sector (such as the installation of some diagnostics, inter-connecting structures and cooling pipes) are carried out.

Standing shoulder to shoulder, two Sector Sub-Assembly tools will suspend the vacuum vessel sectors from the top while carefully positioning and installing—via the rotary motion of the ''wings''—the vacuum vessel thermal shielding and two toroidal field coils.

Made from 800 tons of steel, the 22-metre-tall tools will be capable of supporting, aligning, and stabilizing the vacuum vessel sectors and the toroidal field coils independently through a sophisticated array of precision actuators and sensors. "The assembly of the first sector will take the longest time, as assembly procedures based on the results of tests (involving partial component mockups) are honed via the experience gained as the sequences are performed for the first time on real components," says Emma. At different stages in the sub-assembly process, metrology surveys will be used to verify the components' positions. The final sub-assemblies, weighing a maximum of 1,200 tons, will be transferred by two overhead cranes operating in tandem to the Tokamak Pit.

As part of its procurement contributions to 澳门六合彩高手, the Korean Domestic Agency is responsible for the design and fabrication of the Sector Sub-Assembly tool as well as 128 other purpose-built assembly tools.