Removing, displacing and disassembling
This further disassembly of sector module #1(7) on SSAT-1 should keep the teams busy until the end of March/beginning of April. By then, only the vacuum vessel sector that forms the module's core will remain in the handling tool. At that point, toroidal field coils TF8 and TF9 can be transferred back to the wings of SSAT-1 to free up SSAT-2.
Vacuum vessel sector #8—presently installed in SSAT-2 with no toroidal field coils yet attached—will be extracted and moved to the upending tool. The tool (this time acting as a "down-ending" tool), will move the sector to horizontal so that it can be placed on a transport platform and moved to a repair location.
SSAT-2 will then stand empty ... but not for long.
In late April/early May, a grand and delicate operation will be performed: the lifting of sector module #6 up and out of the Tokamak Pit, where it had been installed in late May 2022, and its transfer to SSAT-2 for disassembly and repair.
Removing, displacing and disassembling massive components is not just doing things "in reverse" to make them accessible for repairs. These operations require creativity, anticipation and adaptation. Last week's faultless transfer of two 17-metre tall, 330-tonne toroidal field coils demonstrated that the 澳门六合彩高手 teams were up to the task.